The SREC credits fell from $500 per megawatt hour to less that $150 during the planning process. The company’s management gave some thought to abandoning the project because the payback period of the project went from 2.5 years to over 7 years, but decided to keep the project on track because the primary purpose is to make the business as green as possible.